The Red Deer Polytechnic Alternative Power Initiative and Alternative Energy Lab included the installation of up to three Mega Watts (MW) of grid-tied alternative power as well as the construction of a new interactive learning lab. The lab is an open, flexible working space with a large mezzanine for storage, and the integrated alternative energy technologies are expected to offset an estimated two-thirds of the institute’s annual electrical consumption.

The Alternative Energy Initiative produces up to three MW of electricity –  one MW is generated from Combined Heat and Power (CHP), and two MW are generated with rooftop and ground-mounted solar cells. The building also features all LED lighting, including an LED lighting retrofit on the building’s exterior.  

Throughout the process, Clark Builders went beyond designing and building the lab with alternative energy sources, and provided consultation and assistance on grant and rebate programs to offset the project costs. With an estimated 5,000 tones in Greenhouse Gas savings—equivalent to eliminating the emissions of about 1,100 vehicles—this project is leading the way in sustainable energy buildings. 

  • Client

    Red Deer Polytechnic

  • Architect

    Manasc Isaac Architects Ltd.

  • Delivery Method

    Design Build

DISCOVER MORE

Albian Central Warehouse

Albian Central Warehouse

Clark Builders constructed a 7,396 sq. m centralized warehouse with a single-storey warehouse and a single-storey office for a major exploration and ...
Fort Chipewyan Solar Farm

Fort Chipewyan Solar Farm

Clark Builders installed a 2.2 MW solar array in Fort Chipewyan, relying on ice roads to transport materials during a small window of opportunity, ...
Nutrien Scissor Creek Office Complex

Nutrien Scissor Creek Office Complex

Clark Builders constructed a new administration and mine dry complex for Potash Corporation of Saskatchewan's Scissors Creek mine expansion, ...
BHP Ekati Diamond Mine

BHP Ekati Diamond Mine

Clark Builders completed the largest construction project ever in Canada's north, including a truck maintenance facility, warehouse, and office ...
Shell Albian Sands Administrative Building

Shell Albian Sands Administrative Building

Clark Builders completed a fast-tracked design-build workforce accommodation project designed for 2,500 people, featuring a commercial kitchen, ...
Red Deer Polytechnic Alternative Power Initiative and Alternative Energy Lab

Red Deer Polytechnic Alternative Power Initiative and Alternative Energy Lab

The Red Deer College Alternative Power Initiative involves installing up to 3 MW of grid-tied alternative power, constructing a new learning lab, and ...

LET’S BUILD THE FUTURE OF CONSTRUCTION TOGETHER

Join us in our aspirations to create more, do more, and connect more Canadian communities than ever.