Skip to main content

Equinix Data Centre

Brampton, ON

Project Description

The Equinix Data Centre in Brampton is a multi-phase refurbishment and expansion delivered within an active, operational data centre campus. The work required precise coordination to maintain uninterrupted operations while increasing capacity and system resiliency.

The project included upgrades to the 903A Data Hall, a 12,000-square-foot space enhanced to support 1 MW of critical power. Improvements included electrical system upgrades with N+1 redundancy, HVAC enhancements, new partitions and security cages, and fire protection and life safety upgrades.

A significant component of the project was the TR-06 expansion, which transformed approximately 175,000 square feet of previously unused space into new data halls, chiller rooms, and office areas. This phase introduced new structural, electrical, and mechanical systems including generators, UPSs, PDUs, and a high-efficiency chilled water plant, supporting up to 15 MW of additional capacity.

Additional HVAC upgrades were completed within an occupied 150,185-square-foot facility, including the replacement of air handling units, dry coolers, make-up air units, associated piping, controls, and rooftop infrastructure.

Delivered within a live mission-critical environment, the project demonstrates the precision and technical coordination required to execute technically complex data centre upgrades and expansions while maintaining operational continuity.

  • Client

    Equinix

  • Size

    337,500 sq.ft. 

DISCOVER MORE

Esker Art Gallery

Esker Art Gallery

Located atop the prominent Atlantic Avenue Art Block, which Clark Builders completed in 2012, in Calgary’s famed Inglewood district, the Esker ...
St. Francis Xavier Church

St. Francis Xavier Church

Clark Builders constructed Camrose's St. Francis Xavier Church, featuring a sanctuary seating 600, a hall seating 350, a chapel, offices, washrooms, ...
Fort Edmonton Park

Fort Edmonton Park

The Fort Edmonton Park project was a comprehensive revitalization endeavor, aimed at elevating and enhancing the park's appeal to ensure it remains ...
Fort McKay Community Centre

Fort McKay Community Centre

The Fort McKay Community Centre, a vibrant space for cultural events, built with local engagement and sustainable practices, reflecting the ...
Okotoks Church

Okotoks Church

Clark Builders constructed a church addition for 360 people with new washrooms, a kitchen area, a gravel parking lot extension, upgraded septic and ...
St. Josaphat Ukranian Catholic Parish Restoration

St. Josaphat Ukranian Catholic Parish Restoration

The St. Josaphat Ukrainian Catholic Church underwent exterior restoration, including masonry, roofing, painting, and wood dome repairs, with the ...

LET’S BUILD THE FUTURE OF CONSTRUCTION TOGETHER

Join us in our aspirations to create more, do more, and connect more Canadian communities than ever.