École Įtłʼò

Yellowknife, Northwest Territories

Project Description

The École Įtłʼò is a brand new school that was built over the same footprint of the original school, which has been demolished. It is a two-storey steel structure with an exterior envelope system and exterior siteworks and concrete. The facility is 46,919 square feet with 18 classrooms, a gymnasium, and a library. It can accommodate up to 572 people. Temporary portable classrooms were installed to accommodate the classes while construction was taking place.

An Indigenous consultant was brought in to provide insights on the facility’s design. Elements such as circular spaces, wayfinding, and culturally significant colour palates were incorporated into the building’s design.

Shortly after starting the project it was discovered that there was a 4.5 meter void under the centre of the school that had not been shown on the geotechnical information taken from around the existing school. This was handled by implementing an increased blasting program, and filling the remaining void with concrete. Revising the siteworks and dropping the main floor elevation by 1.5 meters not only benefited the geotechnical footprint below, but also improved the accessibility of the school.

A significant value to this project was our self-performing the cladding on the school. We first installed an exterior wall consisting of a Torch-On Air Vapour Barrier Membrane, 2 Layers of Mineral Wool Insulation, Full Depth Thermal Clips & related Galvanized sub-girts. This ensured a smooth transition between the profiled prefinished steel, phenolic panel, and fibre cement plank material that made up the cladding.

Originally named the J.H. Sissons school, it was officially renamed École Įtłʼò, honoring the region’s Indigenous culture and language. The project exemplifies culturally responsive design, technical precision, and community engagement.

  • Client

    Government of the Northwest Territories

  • Architect

    Stantec Architecture Ltd.

  • Size

    43,647 sq.ft.

  • Delivery Method

    Lump Sum

DISCOVER MORE

Douglas Elementary School

Douglas Elementary School

Douglas Area Elementary School is a new two-storey school with a tilt-up concrete gymnasium and steel framing, featuring 25 classrooms, a full ...
Robert G. Kuhn School of Business

Robert G. Kuhn School of Business

Trinity Western University’s Robert G Kuhn School of business will be a four-storey structure with natural heavy timber and steel, featuring ...
JH Sissons School

JH Sissons School

JH Sissons New School is a two-storey steel structure that was built over the same footprint of the original school, accommodating up to 572 people, ...
Allard Hall

Allard Hall

Allard Hall is a five-story building with performance spaces, galleries, classrooms, labs, and offices that serves as a hub for visual and performing ...
Escuela Mill Creek School

Escuela Mill Creek School

The new replacement school services K-6 students, with a collaborative team and environmental considerations, featuring a bird’s nest learning ...
Crowfoot School

Crowfoot School

Clark Builders constructed the Siksika Crowfoot Elementary School, featuring cultural elements and cost-saving options, with a steel frame, concrete ...

LET’S BUILD THE FUTURE OF CONSTRUCTION TOGETHER

Join us in our aspirations to create more, do more, and connect more Canadian communities than ever.